2 Nov 2015

Update 4 – Cheltenham Apartments, St. Clair

The Level 2 suspended slab has been poured and we are preparing for the final Level 3 pour which will be completed in November 2015. In the last few days we have also installed precast concrete panels to Level 2 and the remaining panels will be installed early next week. Installation of scaffolding has commenced which will allow us to start working on the facades. 12186821_1015817618440023_5047797245094802622_o 10989097_1015817695106682_7849268066904573485_o 12208535_1015817705106681_6541718386141034065_n 12186421_1015817675106684_7939567101961525099_o